CodingBox Documentation

Cable routes and installation: ducts, burial, aerial, indoor

A fibre link's loss budget is decided on paper; whether the installed plant meets it is decided by how the cable got from A to B — the tension it was pulled with, the radius it was bent to, the slack left in closures, the fire rating chosen for the riser, the depth of the trench. This page covers outdoor and indoor installation methods, the mechanical limits that protect the glass, planning and permits, labelling and documentation, and the installation mistakes that show up years later as unexplained loss.

Outdoor installation methods

MethodHowCable typeTypical useWatch
Duct / conduitHDPE ducts (32–110 mm) with subducts; cable pulled with winch and lubricant or blown (jetted) with compressed airloose-tube, dielectric or armouredurban, campus, along roadspulling tension limit (typ. 1 000–2 700 N), fill ratio ≤ 40 %, duct integrity (mandrel test), water
Microduct / air-blown fibre5–16 mm microducts in a bundle; micro-cables (200 µm fibres) blown 1–2 km per shotmicro-cable, 12–432 fFTTH, metro, incremental fibre addsblowing speed/pressure, duct cleanliness, low-friction cable
Direct burialtrench or plough at 0.6–1.2 m; warning tape and marker postsarmoured (steel or FRP), rodent-protectedrural, long routesdepth by soil and frost line, backfill without stones, locate services first
Microtrenching2–4 cm slot 20–40 cm deep in road surfacemicro-cable in microductdense urban FTTHpavement damage, shallow depth risk
Aerial, lashedcable lashed to a steel messenger strand between polesstandard loose-tuberural, where poles existsag and tension, ice and wind loading, clearance
Aerial, self-supporting (ADSS)all-dielectric cable with aramid strength memberADSSpower-line rights of way, spans 100–1 000 melectric field tracking near HV, hardware, vibration dampers
Figure-8 / dropintegrated messenger; FTTH dropsfigure-8, flat droplast span to buildingsspan ≤ 80 m, service loops
OPGW / wrapfibre inside the ground wire or wrapped on itOPGW, OPPCHV transmission linesutility procedures
Submarinearmoured, repeatered; ship-laidsubmarinesea crossingsseparate discipline

Indoor pathways

PathwayCable ratingNotes
Plenum (air-handling spaces)OFNP / OFCP (NEC), or LSZH per IEC 60332-3 + low smoke in the EUplenum cable is mandatory where air circulates
Riser (vertical shafts)OFNR / OFCRriser-rated or better; firestop every floor penetration
General purpose / horizontalOFN / OFCtrays, conduits, J-hooks every 1.5 m
Under-floor / overhead in DCLSZH; MPO trunks with pulling eyesseparate fibre trays from heavy copper; bend-radius guides at drops
Outdoor → indoor transitionoutdoor cable ≤ 15 m indoors, or indoor/outdoor rated, or transition splice in the entrance facilitygel-filled outdoor cables are not flame-rated
Between buildingsduct with indoor/outdoor cable, or outdoor cable to entrance facilityground armour, lightning consideration

Mechanical limits that protect the glass

ParameterLimitWhy
Pulling tensioncable datasheet (600 N for small indoor, 1 000–2 700 N loose tube, higher for armoured); never pull on fibres, only on strength member via grip/swivelexceeded tension = fibre strain, microcracks, future breaks
Bend radius during installation≥ 20 × cable diameter (under tension)kinks and stress at sheaves
Bend radius installed, no tension≥ 10 × cable diameter; cords ≥ 30 mm (SMF), G.657 cords 15/7.5 mmmacrobend loss (Light in fibre)
Crushdatasheet (typ. 1 000–2 000 N/10 cm)vehicles over surface-laid cable, heavy cable on top in trays
Vertical risemax unsupported vertical run per datasheet (typ. 500 m+ for loose tube with proper clamping)cable weight loads fibres
Temperatureinstallation −10…+50 °C typical; operation −40…+70cold cable is stiff and brittle; gel stiffens
Slack10–20 m at each closure (both directions), 3–5 m at building entries, 1–2 m in panelsre-splicing and re-routing without new cable
Cable tieshook-and-loop, never tight nylon ties on fibreties are the #1 cause of macrobends in racks

Route planning

  1. Survey: existing ducts and their occupancy, poles and their loading, soil, crossings (roads, rivers, rail), other utilities.
  2. Permits and rights of way: road authority, landowners, pole attachment agreements, railway/pipeline crossings.
  3. Diversity: separate physical routes for protection paths (Topologies).
  4. Fibre count and cable type per segment; splice-point and closure locations (manholes, poles, cabinets) at 2–4 km spacing on trunks.
  5. Loss budget per link from the route: length, splices, connectors (Link budget engineering).
  6. Documentation plan: GIS layer, cable/fibre numbering, labelling scheme (TIA-606), test plan.
  7. Safety plan: traffic management, confined spaces, working at height, laser safety (Safety & handling).

Splice points and closures

ItemPractice
Closure placementmanhole, pole, cabinet; accessible, above flood level where possible
Typedome (butt) for trunks, inline for mid-span, wall boxes indoors (Passive plant)
Sealingheat-shrink or mechanical (gel) seals; IP68; re-enterable
Groundingarmour and messenger bonded and grounded at closures and building entries
Fibre organisationtrays by tube colour, splice protectors, bend guides; every fibre labelled
Recordssplice diagram per closure with fibre-to-fibre mapping, photos before closing

Splicing technique: Splicing and termination.

Labelling and documentation

ItemStandard practice
Cable IDunique per cable, printed on jacket at entries and closures
Fibre numberingtube colour + fibre colour → sequential number (1–144…) per TIA-598
Panel portsrack/panel/port with far-end reference
Cordsboth ends labelled with far-end position (Port naming & LEDs)
As-builtGIS route with chainage, closure locations, cable types and lengths, splice diagrams
Test recordsOTDR traces and loss per fibre at commissioning (Testing & measurement)
Change logevery re-splice, re-route, added splitter

Acceptance after installation

  1. Visual: closures sealed, slack stored, labels present, bend radii respected.
  2. Continuity and polarity of every fibre (VFL or OTDR).
  3. Bidirectional OTDR of every fibre at 1310/1550 (and 1625 for bends); splice loss ≤ 0.1 dB, no reflective events above design.
  4. Insertion loss of every link at working wavelengths vs budget.
  5. Documentation handed over and matched to the field.

Installation mistakes that surface later

MistakeLater symptom
Pulled by fibres / over tensionrandom breaks months later; high loss increasing with time
Tight nylon ties, sharp trayswavelength-dependent loss, worse at 1550/1625 (Plant faults)
No slackcannot re-splice after a dig-up without a new cable section
Outdoor gel cable through the buildingfire-code violation; gel migration into panels
Unsealed closurewater, loss rising at 1383/1550, freeze damage
Mixed 50/62.5 µm or SMF/MMF patching2–4 dB or no link (Physical mismatches)
No labels, no as-builthours per incident; wrong fibre cut
Shared trench for "diverse" pathsboth paths cut together

In CodingBox

Installation quality shows up in DDM: a link whose Rx power sits 2 dB below the design value on day one has an installation problem, not a module problem. Recording each module's Tx and Rx at commissioning in CodingBox gives the baseline that separates the two (DDM in the app, Rx power & budget).

Choosing the cable for the route — designs, armour, fire ratings, tensile and crush values: Cable construction; recording what was installed — identifiers, labels, splice schedules, as-built and test archives: Documentation & labelling.